Short Production Run Update

No Tags
Short Production Run Update

We have placed orders for all the components needed and they have begun to rickle in. The anti-glare screen protector has arrived and is already available here in our web store: http://fuzeti.com/accessories/anti-glare-screen-protector.html

There was a small delay with the panel itself but we still expect to receive them in time to ship out on schedule:-) 

The 3D printer is busy printing out parts, and each complete enclosure set takes roughly 16 hours to complete. We expect to begin assembling the PCBs and FDC displays in about a weeks time. Assembly of each unit takes about 12 hours, all by hand:-) The PCB assembly is something that would have been automated in a larger production volume and would've cut down the assembly time of an array of 5 boards to only a couple minutes.

Thanks everyone for your support!